Carquinez Monthly Progress
for March, 2001


Tower T3 East footing floated in,
placed over piles at high tide early Mar 13th

Tower T3 West footing floated in,
placed over piles at high tide early Mar 14th

North Anchorage; excavation
completed, all seal slabs poured

North Anchorage; concret pour
of first lift of connector beam

South Anchorage, lower tier,
concreting seal slab

South Anchorage, lower tier,
concreting seal (detail)

Pier P1 installation of temporary truss;
decking out for link beam construction

Pier P1
truss erection

Pier P1, truss installed and decking out
Arrival of Wirth under-reamer
for rock socket stability for T2 piles
 