Carquinez Monthly Progress
for October, 2000
T3 access bridge pier,
fabricated at Mare Island
View of the south bank
to the north
Adding length to 3 meter piles
at Mare Island
Erecting the 280' truss bridge for
T3 access at Mare Island
North Anchorage shoring work
continues
Working on the north bank for stairwells to access T3
3 meter pile cofer dam set for
pile splice at T3
Cleaning concrete from pile south east east one at T2
Pier One east forms at second lift
& west at first
Splicing, drilling, driving 30" pipe pile & driving sheet pile at the South Anchorage