Carquinez Monthly Progress
for October, 2001


Project Overview

Project overview (night)

South Anchorage Oct 4th cleaning
1st pour upper & mid tier

South Anchorage:
Oct 18th.

South Anchorage and Pier P1, T2 and T3

Dismantling of falsework truss at Pier P1

Tower T2

Tower T3

North Anchorage
backfill early Oct.

North Anchorage backfilled; construction
abutment, roadworks in back in progress.

Template for bridge deck
construction at IHI works (Japan)

Casting sample of suspender link &
rope seperator at Chongquing (China)
 