Carquinez Monthly Progress
for September, 2000


Continued contruction of
T3 footings

Driving of 30" pipe pile at
South Anchorage. (Foundation Construction)

Rock from pile location sww3

Rock from sww1 pile, aprx. 6' in length

Pumping concrete in pile sww3
after cave-in

Pulling spilced rebar cage from pilling
after a cave-in

Rebar cage being set at P1 west

Wet concrete ready for cure, P1 east footing.

North Anchorage excavation
and shoring construction

RT3 retaining wall
at the north end
 