New Joint Venture to replace the East Span of the San Francisco-Oakland Bay Bridge
 
Congratulations to FCI Constructors for landing a joint venture with Kiewit Construction Company and Manson Company to replace the East Span of the San Francisco-Oakland Bay Bridge. This portion of the famous bridge connects Yerba Buena Island and the city of Oakland. Work is now in the planning stage, with construction slated for completion in early 2006. Coming in at $1,043,541,000, the replacement will be known as the "Skyway Project." It includes constructing two parallel, pre-cast segmental concrete bridges. Each bridge will be 2,100 meters long, and 27 meters wide. Each bridge will be comprised of 226 segments, at a total weight of approximately 800 tons.

The bridges will be supported on 28 piers founded on 160 steel-shell, concrete piles 2.5 meters in diameter, and 95 meters long. The joint venture's contract is the second of four contracts for the bridge replacement. The remaining contracts will build the self-anchored suspension span and tower, and demolish the old bridge.

An enormous amount of up-front, off-site work must be completed before construction can begin on this huge and technically challenging project. Sixty people started working full time on April 1, 2002 in a temporary office in Oakland. A permanent 25,000-square-foot office should be ready by June. At its peak the staff on the job will be approximately 120 people.

Dredging and installation of access trestles are scheduled to begin in May 2002. Crews should start installing piles by December, followed by footing boxes and concrete. Planning is well underway for establishing a pre-cast segment construction yard. The first trial test segments will be built before the end of 2002.

Here's the sequence of major components of the construction:

1. Dredge around foundations.
2. Install piles.
3. Install cofferdams.
4. Install and build pile caps.
5. Build pier columns and towers.
6. Set pier table at top of piers.
7. Set precast segments out from pier tables.
8. Pour closure at mid-span.
9. Complete all 24 spans.

continue>>
 
HBG Constructors - A Design-Build and Construction Company Articles catalogue