Project Overview:

Awarded to FCI North in August, 2002, this project for the Santa Clara Valley Transportation Authority (VTA) will create a safer environment for those traveling between California routes 85 and 101. Providing a new northbound 85/101 interchange, the construction will also connect new High Occupancy Vehicle (HOV) lanes to existing carpool lanes, and improve three adjacent interchange ramps.

Four main elements make up phases one and two of this project:

1 - Construction of the first new bridge - the northbound 85 to Shoreline Blvd. off-ramp

2 - Temporary alignment of northbound 85/101 traffic onto this new bridge

3 - Removal of existing northbound 85/101

4 - Construction of the northbound 85/101 overcrossing and the 85/101 HOV lanes

The final phase of this project will be to direct traffic onto the new roadway and complete the Shoreline Blvd. off-ramp. Reconstruction of the Old Middlefield Way overcrossing is ongoing throughout all three phases, with project completion scheduled for August, 2005.

85/101 Project Photos:

2003 Progress Photos

What's New?

Fall 2003

Crew completed final stage of MSE wall 14. Construction of the coping slab and concrete barrier will begin shortly. Crew also began installling MSE walls 3, 4, 9, 10, 11, 12, and 13 simultaneously.

The first stage of Steven's Creek construction is completed. The final stage will start next summer.

Pile driving at AR3 abutment four is complete. The substructure of AR3 will be completed in the up coming weeks.

Falsework of AR3 is being fabricated and will soon be erected. The AR3 bridge currently is the critical path of the project.

Summer 2003

Crews began final stage of MSE wall 14 panel installation. This 3,500 square meter wall with many artistic details will be completed in late August.

Crews are preparing for the construction of the AR3 Bridge Abutment four.

All columns for the SR4A Bridge have been poured. There will be four MSE walls making the abutments of this bridge and preparation of building these walls are underway.

The first phase of Stevens Creek widening has begun, with completion slated for mid October of this year.

Spring 2003

Crews began the first MSE wall construction in May, and will continue for the next 24 months until all 20 walls are built.

FCI also began the installation of 851, 100-ton, precast concrete piling.

Pile driving for nine bents and four abutments will continue through the summer and fall months.

Project Related Links:

Santa Clara Valley Transportation Authority
http://www.vta.org/highways/rte101s.htm

and

http://www.vta.org/highways/rte85101n.htm

 

 

back to top

back to current projects
current projects
   85/101    interchange
   knightdale bypass
   cooper river
   carquinez
   terminal roadways
   university light rail
   oakland
   routes 60/91/215
   foothill toll road
   route 56
   i-680/marina vista
 


employee login  :  site map  :  contact us  :  home  :  terms of use
 
Sitemap
HBG Constructors - A Design-Build and Construction Company Articles catalogue