route 85/87 interchange completion

Project Overview:

The four main sections of this $23.5 million job include the South 85/ North 87 connector separation, North 85/North 87 connector over crossing modification, Southbound Route 87 connector and Guadalupe River bridge widening.

This project, located in Northern California near San Jose, is the completion of an interchange built 12 years ago. Flyover ramps will connect southbound Route 85 to northbound Route 87 and southbound Route 87 to northbound Route 85. The new flyovers will connect to two structures that were partially built during the original construction and will help to remove freeway traffic from local streets.

"One challenge is to keep freeway and light rail traffic flowing through the project, under and around the construction," says project manager Walt Quincy. "Work over or immediately adjacent to the traffic is performed behind protective barriers or done at night during lane closures." Substantial penalties could be incurred if the closures exceed their allowed time periods.

The project is approximately half completed, and is progressing ahead of schedule with falsework erection finished at the end of October. The estimated date of completion is May, 2003.

85/87 Project Photos:

Winter 2002/2003
Summer 2002

What's New?

February/March 2003

All major concrete placement is complete, and falsework removal will begin on the last bridge.

The entire project will be complete by May.

December 2002

The last two deck pours will be completed in late January

Falsework stripping is almost complete

November 2002

Concreting of main flyover completed, followed by falsework stripping

October 2002

Last of the falsework erected

Bridge superstructure construction is in high gear and falsework removal will begin shortly

On schedule for early completion

September 2002

Deck pour on Highway 85

Poured third section of stems on 85 to 87 connector

August 2002

The first third of flyover 1 is constructed with the second third approximately half completed and the last third just starting

Flyover 2 has its columns built, and the last abutment is under construction. Falsework for the superstructure is starting

Bridge 1 widening just finishing

Bridge 2 falsework for the superstructure is erected

Project Features:

A connector separation involving 523-meter, three-framed, prestressed concrete box girder bridge, including a total of 6,068 meters of piling and 6,545 cubic meters of concrete

An over-crossing modification with a 12.5-meter, reinforced concrete bridge with 201 meters of piling, and 328 cubic meters of concrete. This is a 1.83-meter-thick slab bridge to an existing bridge

A southbound route 87 connector with a 477-meter prestressed concrete box-girder bridge of two frames with a total of 2,862 meters of piling, and 3,708 cubic meters of concrete

A bridge widening using a 129-meter concrete box girder bridge with a total of 1,484 meters of piling, and 1,265 cubic meters of concrete

The project will use 16,000 tons of asphalt concrete, 15,000 cubic meters of excavation and 92,000 cubic meters of embankment

Project Related Links:

Santa Clara Valley Transportation Authority
http://www.vta.org/highways/rte8587.htm

 

 

back to top

back to current projects
current projects
   knightdale bypass
   cooper river
   carquinez
   terminal roadways
   university light rail
   i-90 logan airport
   85/87
   oakland
   routes 60/91/215
   foothill toll road
   route 56
   i-680/marina vista
 


employee login  :  site map  :  contact us  :  home  :  terms of use
 
Sitemap
HBG Constructors - A Design-Build and Construction Company Articles catalogue