hbg constructors





  What's New?

September/October 2003

With no elevator yet installed, crews arrive at dawn to climb 18 stories up the narrow staircase onto the strut. From here they look down at the existing bridges from the climbing form system atop a tower that is only half built. They are tying and placing rebar in preparations for pouring the next lift.

Bolted to the towers, this climbing form system is powered by a hydraulic lift, which jumps the platforms up after each lift is poured. The forms look like a gigantic boxes, and hold 80 cubic yards (about 160 tons) of concrete each.

Once the lifts are poured, the sides of the form move away from the tower, and the entire form moves upwards 15 feet. Crews must be very meticulous when performing work at the top of the towers because once the form system advances, there's virtually no way to access that portion of the tower again. With a short three day lift cycle at this stage, these towers will be completed by March 2004.

Each tower's foundation is supported by eleven, 230-foot-long, 10-foot-wide drilled shafts and a 700,000-ton rock island. Seventeen freighters carried the rock from Canada, which was unloaded onto barges and either bottom dumped directly from the barge or placed by crane with a clam shell bucket.

Geotechnical engineers were concerned that the immense weight of the rock islands would settle, causing the riverbed to sink, and the adjacent bridge to lean. Just in case, they installed a flexible bearing system between the piers and superstructure of the adjacent Silas N. Pearman Bridge to allow for this potential movement.

Just west of the towers, HBG personnel are busy working on the Charleston Interchange, with 218 piers and 26,694 feet of roadway. This interchange will connect into Interstate 26 and will also access downtown Charleston's historic Meeting Street.

On Drum Island, construction of all piers in the Cooper River and Town Creek is underway, and small crews are finishing up the stressing. In addition, construction of concrete foundations within cofferdams is underway in the river.

June/July 2003

Approximately 43% of the work has been completed for this bridge - the largest project in South Carolina history. There are currently over 400 craft workers on-site, plus an additional 100 support personnel.

Substructure elements, including columns and pier caps, are in place, and crews have begun work on the superstructure. Both steel and concrete girder placement will be occurring over the next few months.

February/March 2003

The strut at W-15 has been poured along with the first lifts at both columns. The stripping of both columns and the strut form was completed in February.

Both footings have been poured. Rebar for tower lifts 4, 5 and 6 are prefabricated and ready for installation. The climbing forms are being erected and three lifts have been poured.

Placing of rock to the islands is ongoing. Quarry stone (main core) is complete.

90% of the clearing has been done for the Mount Pleasant interchange area. The Coleman detour is underway and is scheduled for the traffic switch on March 8 2003.



January 2003

A three-day, 4800-cubic-yard pour for the main foundation is planned for this month. Tons of concrete will be poured in January, more than at any other time during the project. Concrete will be placed in drilled shafts, tower pier footing, columns and pier caps.

Work on Drum Island continues. The columns on the island will stand taller then the two existing bridges, and will support the superstructure of the new bridge.


December 2002

Drilled shaft work wraps up in Town Creek, and beings in Mt. Pleasant.


November 2002

Engineering is nearing completion, and the footing for the western tower pier is being formed.


October 2002

All drilled shafts are now installed and preparatory work for the footing on the west tower should make it possible for the first major footing pour to occur in mid October.

Crews have installed over fifty percent (145) of the drilled shafts required for the interchange work. Eighty columns have been constructed, and the project’s first sizable bent cap is now completed. This interchange will tie into I-26 and will feature two flyover bridges.

Crews on Drum Island have nearly completed the trestles and access roads that will allow working on the island. Several work yards have been set up where rebar cages for the main piers are being tied. During installation, these unwieldy rebar cages will be installed using a tilting frame to assist with standing them without deforming the shape.

Crews must set each cage in one piece because they will have only 12 hours to complete the splicing of the bars in the drilled hole. This time restriction is based on the needs of commercial shipping traffic, and tide fluctuations of five to seven feet.


September 2002

Drilled caisson work has begun for the 10' shafts.

Crews have started pouring the concrete base for the first pier. Construction of the pier will commence immediately after that.

 

 

 

 

 

back to top

back to current projects
current projects
   85/101 interchange
   knightdale bypass
   cooper river
   carquinez
   terminal roadways
   university light rail
   oakland
   routes 60/91/215
   foothill toll road
   route 56
   i-680/marina vista


employee login  :  site map  :  contact us  :  home  :  terms of use
 
Sitemap
HBG Constructors - A Design-Build and Construction Company Articles catalogue