hbg constructors
about hbg business units hbg projects equipment sales hbg careers



Project Overview:

This $15.5 million FCI South job began in late November 2001. The project's components include bridge widening, pavement rehab and numerous safety features on highway routes 60, 91 and 215.

This project is especially challenging because it requires two lane closures on one of Southern California’s most traveled freeways. All work must be completed between 9 p.m. and 5 a.m. as to avoid major traffic delays. Crews must demolish existing pavement, pour concrete and allow 4.5 hours for the concrete to cure all within this eight-hour window. This project is expected to be completed winter, 2003.

Route 91 Project Photos:

Spring 2003

What's New?

Fall 2003:


Concrete paving operations on the final phase are complete.

Joint sealing and permanent barrier construction ongoing throughout November.

Spring 2003:

Project approaches final stage.

Work on westbound structures ongoing this summer, including steel girder erection.

Eastbound structures were completed in February.

Winter 2002/2003:

Work on the inside and outside eastbound widening is nearing completion.

Existing pavement rehabilitation work will begin shortly.

The project is approximately 50% complete.

Summer 2002:

The first stage of this project is complete and the second of the four stages began at the end of July 2002.

Bridge widening, drainage and pavement rehab will continue concurrent with other operations.

 

back to top

back to current projects
current projects
   85/101 interchange
   knightdale bypass
   cooper river
   carquinez
   terminal roadways
   university light rail
   oakland
   routes 60/91/215
   foothill toll road
   route 56
   i-680/marina vista


employee login  :  site map  :  contact us  :  home  :  terms of use
 
Sitemap
HBG Constructors - A Design-Build and Construction Company Articles catalogue